    当前位置:英超下注>英超下注>防止钢结构安装出现偏差的措施!

    防止钢结构安装出现偏差的措施!

    来源:http://lasimao.com/ 日期:2019-10-24 发布人:admin

      YOUSHI,YOUYUZHUNBEIGONGZUOZUODEBUHAO,YINCIGANGJIEGOUZAIANZHUANGGUOCHENGZHONGHUICHANSHENGPIANCHA。 RUGUOFASHENGPIANCHA,KENENGHUIZAISHIGONGQIJIANDAOZHIANQUANSHIGU。

      Sometimes, due to poor preparation, the steel structure in the installation process will produce deviations. If deviation occurs, safety accidents may occur during construction.

      1.DUIGANGJIEGOUXIANCHANGJINXINGXIANCHANGJIANCHA,JISHIJIUZHENGBIANXINGHEGUODUHEGE。 TONGGUOCESHIHOU,JIKEANZHUANG。

    英超下注  1. On-site inspection of steel structure to correct deformation and over-qualification in time. After passing the test, it can be installed.

    英超下注  2.JIANCHABINGXIAOZHUNCELIANGYIQISHIFOUWANHAO,JILIANGYANZHENGSHIFOUGUOSHI,BINGQUEBAOCELIANGYIQIDEZHUNQUEXING。

      2. Check and calibrate the integrity of the measuring instruments, verify the obsolescence of measurement, and ensure the accuracy of the measuring instruments.

      3.ZAICHANSHENGGANGJIEGOUDEYASUOBIANXINGHEJIETOUHANFENGDESHOUSUOBIANXINGZHISHI,YINGKAOLVGANGJIEGOU。 SHIGONGQIJIANYANGEKONGZHIHANJIESHOUSUOBIANXING,BINGZHUYIJICHUCHENJIANGDEBIANHUA。

    英超下注  3. When the compression deformation of steel structure and the shrinkage deformation value of weld joint are produced, the steel structure should be considered. During construction, welding shrinkage deformation should be strictly controlled, and the change of foundation settlement should be paid attention to.

      4.XUANZESHIDANGDESHIJIANCELIANGYIQUEBAOCELIANGJINGDU。

      4. Choose appropriate time measurement to ensure measurement accuracy.

      5.ANZHUANGGANGJIEGOUHOU,BIXUCAIQUKEKAODELINSHIGUDINGCUOSHIHUOXINGCHENGWENDINGDEZHUANGZHI,YIQUEBAOGANGJIEGOUSHIGONGDEANQUANXING。

     

    英超下注  5. After installing the steel structure, reliable temporary fixing measures or stable devices must be taken to ensure the safety of the construction of the steel structure.

      6.ANZHUANGPIANCHACHAOGUOYUNXUPIANCHADEGANGJIEGOUYINGJISHIDIAOZHENG。 DUIYUWUFADIAOJIEDEBUPINGHENGGANGJIEGOU,YINGJILUCELIANGZHI。 SHEJIHEYOUGUANBUMENTONGYIHOU,YINGJIANGQIANZHENGCUNDANG。

      6. The steel structure whose installation deviation exceeds the allowable deviation should be adjusted in time. For unbalanced steel structures that cannot be adjusted, the measured values should be recorded. The visa shall be filed with the consent of the design and relevant departments.

      YISHANGSHIFANGZHIGANGJIEGOUANZHUANGPIANCHADEYOUXIAOCUOSHI。 ZAICAOZUOZHONG,YINGYANGEANZHAOCAOZUOGUIFANJINXINGCAOZUO。 YOUYUGANGJIEGOUDEANZHUANGBUSHIYIGEJIANDANDEXIAOGONGCHENG,YINCIFEICHANGYOUBIYAOZHANGWOCHANPINDEXIANGGUANJIANZHUZHISHI。

      The above are effective measures to prevent installation deviation of steel structure. In operation, the operation should be carried out in strict accordance with the operational specifications. Since the installation of steel structure is not a simple small project, it is necessary to master the relevant building knowledge of products.

    英超下注ZIXUNREXIAN:15865282363    15253185838

    英超下注DIZHI:JINANSHILICHENGQUHEHUALUWANGJIAZHACUN

    Copyright © 2019 JINANHUIXINCAIGANG All ReservedBANQUANSUOYOU